Projects

29Sep

CURRENT 4TH QUARTER2014 PROJECTS

Current 4th Quarter Projects from Central Paving Co. Inc.

Broadway Interchange

Highlights: This project consists of replacing the existing Broadway Overpass with a Single Point Interchange and widening of Interstate I-84 to accommodate a 3rd March of 2014 and has an estimated completion date of fall of 2015. The existing structure was built in 1969.

Owner: Idaho Transportation Department
Dates: March 1014 – Late Fall 2015

Roosevelt Street, Overland Road to Cassia Street Reconstruction

Highlights: This project consists of widening Roosevelt to new sidewalks, Bike Lanes, Roadway and a new asphalt overlay. Work commenced in June and should be complete by early October.

Owner: Ada County Highway District
Date: June 12 to Early October

Ada County Landfill Main Entrance Reconstruction

Highlights: Project consists of the removal of approximately 1⁄2 mile of roadway, re-grading, shaping, shouldering and repaving.

Owner : Ada County
Dates: September 3, 1014 to October 8th

City Center Plaza

Highlights: City Center Plaza is a mixed use commercial, office, retail and convention center with an underground transportation terminal. The work consists of removing miscellaneous structures, parking lot and the excavation approximately 51,000 cubic yards of excavation.

Owner: Gardner Company
Completion: Fall of 2014

Boise Airport: Taxiway K Realignment & Rehabilitation of Taxiways J, F & K

Highlights: Project work consists of the rehabilitation of existing taxiways, pavement milling, pavement demolition, excavation, base courses and the placement of new pavement.

Owner: City of Boise
Dates: September 22, 2014 to spring of 2015

Search

Project Categories

Paving Projects

News Archive

 Idaho ACG
 Proud partners with Osha